We are currently focused on building the six new underground stations, constructing the concrete bases that will hold the SkyTrain tracks in the tunnels, and installing tracks on the Elevated Guideway. We provide ongoing updates about construction in advance to email subscribers, through alerts to traffic news outlets, social media posts and here on our website. Please see notifications below and contact us if you have specific questions about what’s happening currently on and near Broadway. Register to receive construction notices for specific station areas and general updates here.
You can access businesses, services and residences on Broadway throughout construction. Visit our maps page to see an interactive map and other resources, such as parking and access maps for the station areas along the Broadway corridor which provide alternative travel and parking options for people visiting Broadway businesses, services or residences.
Raise the Roof! First Roof Sections Installed at New Stations
Anatomy of a Station – How the BSP Stations Are Built
Going Up – First Escalators Installed at South Granville Station
TBM Disassembly Complete
Construction Forecast
Summer Scenes on Broadway
Worker Spotlight
Night work for piezometer, geotechnical, and CCTV inspections between future station locations continues in 2024 (click to view detailed notice)
BSPC continues to monitor ground and water conditions as well as utilities across the alignment
Geotechnical, piezometer and closed-circuit TV (CCTV) readings will be taken overnight throughout 2024
Temporary single-lane closures of up to one hour for CCTV monitoring locations with reduced speeds and detours around the work as required
For geotechnical monitoring device and piezometer readings, there will be short-term traffic lane shifts (about 15-minutes in duration) at the test locations
A traffic truck with direction lights will indicate the lane shift, while crews take the geotechnical or piezometer readings
We are maintaining four lanes of traffic in station areas on Broadway during weekday peak periods, with lane closures planned primarily in off peak times.
Between station areas, six lanes of traffic are open during rush hour, with on-street parking in some locations in off-peak times.
Off peak times include: 10 a.m. to 3 p.m. weekdays and weekends.
Please expect temporary lane closures for deliveries, crane movement of materials into the station areas and work on the traffic deck.
Great Northern Way-Emily Carr Station
Great Northern Way-Emily Carr hours of work: 6 a.m. to 11 p.m. Intermittent night work.
Elevated guideway typical hours of work: 6 a.m. to 9 p.m. Intermittent night work.
Crews are building the new station, including concrete and rebar activities with increased deliveries of supplies.
Track installation is ongoing on the elevated guideway.
Work to build the future Great Northern Way-Emily Carr Station continues through fall 2024 – includes night work (click to view detailed notice)
With major station structures now complete, crews are focused on completing the tunnel structures that connect the elevated guideway to the future station, as well as the underground station structure.
Regular work hours are from Monday to Friday from 6 a.m. until 11m.
There may be occasional work that starts earlier or work on Sunday and holidays.
Track installation on the elevated guideway continues through fall 2024 – includes intermittent night work (click to view detailed notice)
Construction of the structure was completed in spring 2024 and work to install tracks for the SkyTrain will continue through the fall.
Regular work hours are Monday to Saturday from 6 a.m. until 9 p.m. There may be occasional work on Sundays and holidays.
Mount Pleasant Station
Typical hours of work: 6 a.m. until 10 p.m. Intermittent night work.
Crews are building the new station, including concrete and rebar activities with increased deliveries of supplies.
Deliveries to site require intermittent closures of less than 30 minutes in the southbound curb lane on Main Street between E. Broadway and E. 10th Avenue.
Mount Pleasant Station construction continues through fall 2024 – includes intermittent night work (click to view detailed notice)
Through the fall, crews continue to focus on constructing the underground station, including walls and floors.
Regular work hours are Monday to Saturday from 6 a.m. until 10 p.m. There may be occasional work on Sundays and holidays.
Welding, waterproofing, and rebar installation, carpentry and mechanical and electrical work is being carried out on site.
Broadway-City Hall Station
Typical hours of work: 6 a.m. until 10 p.m. Intermittent night work.
Crews are building the new station, including concrete and rebar activities with increased deliveries of supplies.
Excavation: includes intermittent rock breaking, securing wall support, and trucking activities to remove material.
Lane reductions on Cambie Street due to construction of the Canada Line/Millennium Line underground connections.
Work on Cambie Street east sidewalk between Broadway and 10th Avenue to complete Canada Line/Millennium Line underground connections. Day and night work with intermittent pedestrian detours after 8pm.
Broadway-City Hall Station construction continues through the fall – includes intermittent night work (click to view detailed notice)
Work is focused on constructing the walls, columns, floors and roof of the underground station.
Crews are also working along Cambie Street from W. Broadway to W. 10th Avenue to connect the future Millennium Line extension to the existing Canada Line station.
Regular work hours are Monday to Saturday from 6 a.m. until 10 p.m. There may be occasional work on Sundays and holidays.
Some elevated noise during specific activities.
Oak VGH Station
Typical hours of work: 6 a.m. to 10 p.m. Regular night work.
Crews are building the new station, including concrete and rebar activities with increased deliveries of supplies.
Through the fall, crews continue to focus on the construction of the second level of the underground station structure.
Regular night work is ongoing: hours can range from 10 p.m. to 5 a.m.
Temporary traffic changes and increased trucking activity related to materials delivery and concrete pours.
South Granville Station
Typical hours of work: 6 a.m. to 10 p.m. Regular night work.
Crews are building the new station, including concrete and rebar activities with increased deliveries of supplies.
Construction of the South Granville Station continues through fall 2024 – includes night work – (click to view detailed notice)
With the first escalators installed and significant work completed in the station, crews are focused on constructing the second station level of the station under the traffic deck.
Regular night work is ongoing; hours can range from 10 p.m. to 5 a.m.
Temporary traffic changes and increased trucking activity related to materials delivery and concrete pours.
Arbutus Station
Typical hours of work: 7 a.m. to 10 p.m. Regular night work.
Crews are building the new station, including concrete and rebar activities with increased deliveries of supplies.
W. Broadway reduced to one lane in each direction for material deliveries and concrete work.
There will be one lane in each direction on W. Broadway between Arbutus and Burrard Street at all times.
Left turns from W. Broadway onto Cypress Street and from W. Broadway westbound onto Maple Street will be allowed at all times.
Maple Street north of W. Broadway will be closed to vehicles and cyclists.
Cypress Street north of W. Broadway will be reopened to vehicles and cyclists to facilitate north-south access to the neighbourhood and businesses on the north side of W. Broadway.
Cyclists are encouraged to use the Arbutus Greenway detour via Cypress Street, W. 7th Avenue and W. 10th Avenue.
On Friday, June 28, the first roof concrete pour will take place on W. Broadway, between Cypress and Maple streets.
Over the coming months, there will be concrete pours of varying volumes. For the subsequent major pours, set up will begin as early as 5 a.m. and continue until 10 p.m.
Expect elevated noise related to trucking. Concrete trucks are required to have their engines running at all times to keep their drums turning, and to use traditional back-up alarms for crew safety.
Broadway will be reduced to one lane in each direction during the work and traffic control personnel will help manage traffic during all work.
Low noise work continuing overnight to finish related activities.
Work will continue inside the tunnels to build the concrete base for track installation and install track and other systems.
Crews are excavating and building the multiple service passages between the twin tunnels.
While crews work inside the tunnels, ventilation fans will be in operation at each station as they play a crucial role in maintaining optimal air quality within the tunnels.
While tunnel activities take place below ground, some activities such as soil and debris removal, concrete pours, and material deliveries will require equipment operating at street level at the future station sites.