We are currently focused on building the six new stations, installing SkyTrain tracks, and completing the interiors of the tunnels. We provide regular updates about construction to email subscribers, on social media, and here on our website. Please see notifications below and contact us if you have any questions.
Broadway remains open throughout construction, with access to businesses, services and residences maintained at all times. Check our maps page for up-to-date parking and access maps of all Broadway stations.
Two Ways Broadway Subway Stations Are Connecting to the City
How Crews “See” When Working Underground
Construction Forecast
Broadway Is Open
Worker Spotlight
Great Northern Way-Emily Carr Station
Great Northern Way-Emily Carr hours of work: 6 a.m. to 10 p.m. Intermittent night work.
Elevated guideway typical hours of work: 6 a.m. to 9 p.m. Intermittent night work.
Crews are building the new station, including concrete and rebar activities with increased deliveries of supplies. Intermittent hydro vac activities.
Track installation is ongoing on the elevated guideway.
Spring 2025 update on Great Northern Way-Emily Carr Station construction – includes intermittent night work – (click to view detailed notice)
Work at the future Great Northern Way-Emily Carr Station continues to progress upwards and, throughout spring 2025, work will focus on constructing the underground station as well as the headhouse. This includes regular concrete pours for the station structure, with larger pours to construct the remaining station roof sections.
Regular work hours are from Monday to Friday from 6 a.m. until 10 p.m. There may be occasional work that starts earlier or work on Sunday and holidays.
Temporary lane closures and changes to pedestrian and cycling routes to accommodate deliveries and trucking activity.
Some elevated noise during specific activities.
Rail track welding starting at elevated guideway in Spring 2025 – includes intermittent night work – (click to view detailed notice)
Work to install SkyTrain tracks at the elevated guideway is expanding this spring. Crews will begin welding pieces of rail together at the elevated guideway site and then transporting them into the tunnels and onto the elevated guideway for installation.
Regular work hours are Monday to Saturday from 6 a.m. until 9 p.m. There may be occasional work on Sundays and holidays.
Temporary traffic changes related to the delivery of materials.
Some elevated noise during specific activities.
Mount Pleasant Station
Typical hours of work: 6 a.m. until 10 p.m. Intermittent night work.
Crews are building the new station, including concrete and rebar activities with increased deliveries of supplies.
Deliveries to site require intermittent closures of less than 30 minutes in the southbound curb lane on Main Street between E. Broadway and E. 10th Avenue.
Two concrete pours will take place on Thursday, April 17. Work hours:
5 a.m. to 10 a.m. on Main Street, with the first concrete truck arriving around 6 a.m.
6 a.m. to 1 p.m. on Quebec Street, with the first concrete truck arriving on site around 7 a.m.
There will be two concrete pump trucks on site: One concrete pump truck will be set up on the west side of Main Street south of E. Broadway; a second concrete pump truck will be set up inside the construction site on Quebec Street south of E. Broadway.
Spring 2025 update on Mount Pleasant Station construction – includes intermittent night work – (click to view detailed notice)
Throughout spring 2025, activities will continue to focus on constructing the underground station, as well as the emergency exit and ventilation shaft on Quebec Street. This includes regular concrete pours for the station structure, with larger pours to construct the remaining station roof sections under the traffic deck.
Regular work hours are Monday to Saturday from 6 a.m. until 10 p.m. There may be occasional work on Sundays and holidays.
Temporary traffic changes related to the delivery of materials and concrete pours.
Some elevated noise during specific activities.
Broadway-City Hall Station
Typical hours of work: 6 a.m. until 10 p.m. Intermittent night work.
Crews are building the new station, including concrete and rebar activities with increased deliveries of supplies.
Lane reductions on Cambie Street due to construction of the Canada Line/Millennium Line underground connections.
Work on Cambie Street east sidewalk between Broadway and 10th Avenue to complete Canada Line/Millennium Line underground connections.
April 16: Work hours are from 8 a.m. to 12 p.m. The first concrete truck will arrive at around 9 a.m.
April 17: Work hours are from 7 a.m. to 4 p.m. The first concrete truck will arrive at around 8 a.m.
Please note that concrete trucks are required to have their engines running at all times to keep their drums turning, and to use traditional back-up alarms for crew safety.
During large concrete pours, there may be times when additional holding areas for concrete trucks are temporarily required.
Spring 2025 update on Broadway-City Hall Station construction – includes intermittent night work – (click to view detailed notice)
Throughout spring 2025, work will focus on constructing the concourse-level walls, columns, and roof of the underground station. Work on Cambie Street between W. Broadway and 10th Avenue will continue to construct the connections to the Canada Line Station.
Regular work hours are Monday to Saturday from 6 a.m. until 10 p.m. There may be occasional work on Sundays and holidays.
Temporary lane closures and changes to pedestrian access to accommodate deliveries and trucking activity.
Some elevated noise during specific activities.
Oak-VGH Station
Typical hours of work: 6 a.m. to 10 p.m. Regular night work.
Crews are building the new station, including concrete and rebar activities with increased deliveries of supplies.
Excavation of the vent shaft and emergency exit is ongoing near Oak Street. Includes intermittent rock breaking.
Throughout spring 2025, work on the future Oak-VGH Station continues to progress upwards, closer to the traffic deck and will focus on the second level of the station. This includes regular concrete pours for the station structure, with larger pours to construct the station roof sections.
Typical hours of work are from Monday to Saturday from 6 a.m. until 10 p.m. There may be occasional work that starts earlier or work on Sunday and holidays.
Temporary traffic changes related to materials delivery and concrete pours
Some elevated noise during specific activities
South Granville Station
Typical hours of work: 6 a.m. to 10 p.m. Regular night work.
Crews are building the new station, including concrete and rebar activities with increased deliveries of supplies.
Utility work continues in the laneway east of Granville Street between W. 10th Ave and W. Broadway.
Starting on Monday, April 14
Daytime work: 7 a.m. to 7 p.m. Focus is on preparation of existing utilities, pavement cutting, excavation and backfilling.
This work is expected to continue for approximately three weeks.
This work is sequential, so some noisy activities will need to happen after 10 p.m. We will make every effort to minimize these occasions when possible.
Spring 2025 update on South Granville Station construction – includes intermittent night work – (click to view detailed notice)
Throughout spring 2025, we will focus on the second level of the station. Activities include regular concrete pours for the station structure, the relocation of key utilities in the area, and track installation in the tunnels.
Typical hours of work are from Monday to Saturday from 6 a.m. until 10 p.m. There may be occasional work that starts earlier or work on Sunday and holidays.
Temporary traffic changes related to materials delivery and concrete pours.
Some elevated noise during specific activities.
Arbutus Station
Typical hours of work: 7 a.m. to 10 p.m. Regular night work.
Crews are building the new station, including concrete and rebar activities with increased deliveries of supplies.
W. Broadway reduced to one lane in each direction for material deliveries and concrete work.
Throughout spring 2025, crews will continue to work on the upper levels of the station and roof. This includes regular concrete pours at our largest station and constructing the concrete lining of the twin tunnels that extend 60 metres west of the station.
Typical hours of work are from Monday to Saturday from 7 a.m. until 10 p.m. There may be occasional work that starts earlier or work on Sunday and holidays.
Temporary traffic changes related to materials delivery and concrete pours.
Work will continue inside the tunnels to build the concrete base for track installation and install track and other systems.
Crews are excavating and building the multiple service passages between the twin tunnels.
While crews work inside the tunnels, ventilation fans will be in operation at each station as they play a crucial role in maintaining optimal air quality within the tunnels.
While tunnel activities take place below ground, some activities such as soil and debris removal, concrete pours, and material deliveries will require equipment operating at street level at the future station sites.